Nylon Cord 1.5m tied both ends in a single closed loop, folded against itself for 2 times. 
 

Main stand already bolted on the frame. Upper spring holding screw in place (Be careful it locates medial to the exhaust pipe, so you must let it cooled down as the space is very limited there. A thin white string is used to keep the stand in elevated position )
 
 
 
The smaller and longer spring is first to be pulled into place (as the upper end of the thinner spring sit more medial on the holding bolt). Pulling effort is alround 20kg. I use my right foot to step against the foot rest, counteracting the pulling force. The thicker spring should  snap into the main stand anchor  by itself if the pulling axis is correct.


It takes 15 minutes to complete the job.